Site investigation, surveying and setting out

Desk study (maps, records), site reconnaissance, trial pits and boreholes to establish soil type, bearing capacity, water table, services and access.

Notes for this topic 1 file, in order

Create a free account to download PDFs.

  1. PDFSite investigation, surveying and setting out – Building Technology and Design notes (ZIMSEC A Level)47.1 KB

Site investigation

Desk study (maps, records), site reconnaissance, trial pits and boreholes to establish soil type, bearing capacity, water table, services and access.

Levelling

Instruments: dumpy and automatic levels, staff, and benchmarks (BM). Readings: backsight (BS), intermediate sight (IS) and foresight (FS).

  • Height of collimation method: HPC = RL + BS; RL = HPC − IS or FS.
  • Rise and fall method: compare consecutive readings; arithmetic check ΣBS − ΣFS = Σrise − Σfall = last RL − first RL.

Worked example: A backsight of 1.250 m is taken on a benchmark of RL 100.000 m. A foresight of 2.100 m is taken on a peg. Find the reduced level of the peg.

HPC = 100.000 + 1.250 = 101.250; RL = 101.250 − 2.100 = 99.150 m

Setting out

Base line and building line; 3-4-5 triangle and theodolite for right angles; checking diagonals; profiles and corner pegs; transferring levels with a level or water level; excavation depths from reduced levels.

Modern methods

Total stations and GPS for accurate surveying; building information modelling (BIM) introduction.

Exam tip: Always do the arithmetic check in levelling tables – it confirms your reduced levels.

Check yourself

  1. What is a benchmark?
  2. The HPC is 52.400 m and a staff reading is 1.850 m. Find the RL.
  3. Why are the diagonals of a rectangular building checked?
Show answers
  1. A fixed point of known reduced level used as a reference.
  2. 50.550 m
  3. Equal diagonals confirm the corners are square.