Topic 1 of 6 · Form 5
Site investigation, surveying and setting out
Desk study (maps, records), site reconnaissance, trial pits and boreholes to establish soil type, bearing capacity, water table, services and access.
Notes for this topic 1 file, in order
Create a free account to download PDFs.
Site investigation
Desk study (maps, records), site reconnaissance, trial pits and boreholes to establish soil type, bearing capacity, water table, services and access.
Levelling
Instruments: dumpy and automatic levels, staff, and benchmarks (BM). Readings: backsight (BS), intermediate sight (IS) and foresight (FS).
- Height of collimation method: HPC = RL + BS; RL = HPC − IS or FS.
- Rise and fall method: compare consecutive readings; arithmetic check ΣBS − ΣFS = Σrise − Σfall = last RL − first RL.
Worked example: A backsight of 1.250 m is taken on a benchmark of RL 100.000 m. A foresight of 2.100 m is taken on a peg. Find the reduced level of the peg.
HPC = 100.000 + 1.250 = 101.250; RL = 101.250 − 2.100 = 99.150 m
Setting out
Base line and building line; 3-4-5 triangle and theodolite for right angles; checking diagonals; profiles and corner pegs; transferring levels with a level or water level; excavation depths from reduced levels.
Modern methods
Total stations and GPS for accurate surveying; building information modelling (BIM) introduction.
Check yourself
- What is a benchmark?
- The HPC is 52.400 m and a staff reading is 1.850 m. Find the RL.
- Why are the diagonals of a rectangular building checked?
Show answers
- A fixed point of known reduced level used as a reference.
- 50.550 m
- Equal diagonals confirm the corners are square.
Questions about this topic (0)